CISWorld.com Products Directory Submit Profile News Events Articles Open RFP Submissions CISWorld Profile

INDUSTRY PUBLICATIONS

American Gas

Electric Energy

Electric Light & Power

Electric Perspectives

Electricity Transmission & Distribution
EnergyBiz

Global Energy Business

PennWell
Pileline & Gas Journal
Platts

Public Power

Public Utilities Fortnightly

 

 

CIS Installation Experience

By Greg Galluzzi, Senior Vice President, Five Point Partners | May 2009

People are always curious about what is taking place in the CIS marketplace. It is not easy tracking all of the different initiatives. While one utility market segment may be extremely busy with CIS projects, others may have minimal activity. This article attempts to provide you with insight into what the market is experiencing in terms of CIS projects and in particular CIS installation efforts.

What we do know about CIS initiatives within the North American utility industry is that of the utilities who are engaged in a CIS project:

  • 50% are installing a new CIS,
  • 35% are selecting a new CIS, and
  • 15% are planning or studying a potential CIS replacement effort.

In addition, when examining 25 utilities who have installed a new CIS solution in the past five years we discover the following:

  • The largest utility in the group serves 700,000 customers and the smallest serves 32,000 customers with the average serves160,000 customers.
  • The shortest installation timeframe was 12 months, the longest installation timeframe was 36 months, and the average installation timeframe was 20 months.
  • The average cost to implement the new CIS was $46.21 per customer which included CIS hardware, software, services, extended CIS software products, and in most instances the use of a solution integrator.
  • The annual maintenance percentage calculated using the software list price was between 22% and 26%.
  • The systems implemented by this utility group included: Harris-Advanced, Harris-Cayenta, Harris-Northstar, Oracle CC&B, SAP CCS, and Ventyx CIS.

Utilities engaged in a CIS installation effort find that it is imperative to closely manage these risky projects. The following are aspects of the CIS project which these 25 utilities constantly monitored in order to insure the success of their initiative.

Customer and Vendor Expectations. Although formal contract documents were developed, signed, and agreed to by both parties, several details arose during the implementation which became the source for conflict and disagreement. The utility focused on resolving these conflicts and maintained realistic expectations regarding the delivery and timing of all aspects of the CIS solution.

Project Resources. One of the biggest headaches was staffing the project with experienced vendor personnel and talented utility staff. Most of the utilities had to release their most experienced personnel to work on the project while still conducting business and maintaining high levels of customer service.

Project Scope. As detailed design activities progressed additional CIS components were included or excluded from project scope. The utilities worked to minimize the number of project scope changes, identified out-of-scope items, and they followed a structured project change request process.

Project Cost. The utilities closely monitored project budget, actual expenditures in the current period, actual expenditures for the project, estimates to complete for the project, and actual cost projections in comparison to project budgets. In addition, they reviewed dollars associated with any project change requests to determine fairness and impact to the project.

Project Schedule. The utilities closely monitored project activities and their progress in relation to the project baseline. For each primary activity this included; the tracking of percentage complete and the projected end date; the status of project milestones with the identification of pending, past due, and critical path milestones; and, the status of financial milestones.

Project Risk. During the course of the project several issues arose, some of which had the potential to impact the successful CIS implementation. The utilities identified areas of risk which may have impacted the project timeframe, project budget, system functionality, or other project components as identified.

Contract Terms & Conditions. The utilities monitored vendor(s) performance in relation to contracted terms and conditions and the agreed upon statement of work. Any discrepancies were identified and reported for subsequent resolution.
The following are common issues faced by utilities who are implementing a new CIS. If not properly addressed these individual issues may ultimately impact the ability to successfully implement the CIS solution.

Mobilization and Staffing. Some projects found their vendor was slow to mobilize and staff the project. In addition, a few of the people proposed and identified in the Statement of Work were not the ones who showed up for work – instead they tended to be less qualified and experienced.

Retaining Key Project Resources. Key resources assigned to the project were not always staffed for the duration of the project because vendors who staff multiple projects tend to move their resources around. For example, one project lost five key vendor personnel to other projects.

Staffing the Project with Utility Personnel. Operationally, many utilities are currently faced with low production staffing levels, hiring freezes, and a reduction in overtime pay. As a result many utilities faced resource issues regarding serving the customer and staffing the project. In several instances, they failed to backfill positions allowing critical resources to staff the project. These critical personnel found themselves doing their regular job and trying to work on the project full-time.

Utility Resource Utilization. Many times the work program and associated schedule did not take into consideration the utility’s ability to staff the project and complete the work assignments in a timely fashion. Project management must conduct resource loading and leveling activities to insure the work assignments and timeframes are realistic.

Project Team Socialization and Collaboration. Typically numerous individuals from many different companies participated in the project. The impact on the project was a complex organization structure and staffing with many roles and responsibilities – some of which overlapped. It is imperative to introduce people to the project and to insure each person understands their specific roles and responsibilities.

A Comprehensive Work Program. Most projects were managed with limited work programs. Project work programs need to contain project activities, project milestones, and dependencies. It should be used with a rescheduling feature to identify impacts to the project critical path and movement of project milestones including the project go-live date.

Lack of Work Direction. Utilities typically looked to the vendor for work direction and assistance in completing project assignments. However, in some instances the vendor focused only on their work assignments and left the utility to their own devices. Vendors must lead utilities through the process to insure both the system and the business are ready for production.

Operating Platform Late Decision. In some cases the decision on which platform to use was left to be determined during the installation phase. As several options exist regarding operation of the CIS including: in-house, hosted, and outsourced platforms, vendors and utilities found themselves scrambling to define, design, and implement the hardware infrastructure to support development activities.

Slow Bill Redesign Activities. Next to conversion, the leading cause of missed go-live dates was the bill print not being ready. Successful utilities started their bill redesigned process early in the installation phase in order to be ready for go-live.

Slow Scope Confirmation Process. In cases where a clearly defined scope was not in place, the project spent considerable time on confirmation and design activities leading to a defined scope. This left less time for subsequent development, testing, acceptance, and go-live preparation activities.

Excessive Third Party Interfaces. Frequently overlooked was the complexity and time requirement to develop third party CIS interfaces. For example, a bank may require 180 days to test remittance processing for the new scan line. This work effort must be considered and built into the project timeline.

Identification and Development of Reports. When the identification of new reports to be developed was done late in the installation process the utility found itself struggling to finish report development by the go-live date. In these cases, many reports had to be developed and implemented in a post go-live period.

Installation of the CIS Data Warehouse. One of the biggest selling points of a new CIS is the capabilities demonstrated around the new CIS data warehouse. Unfortunately, most of the projects did not adequately allow sufficient time to train on the tool and develop specific use of the warehouse by the utility. Much to the dismay of everyone, this work is typically pushed to after go-live.

Project Behind Schedule. At one time or another, many projects fall behind schedule. Usually, once a project falls behind schedule it is tough to catch up. It is imperative that the utility focuses on monitoring the schedule and working as efficiently as possible to stay on schedule.

New Go-Live Date. If the project fell behind schedule, the utility assessed impact to the go-live date. Many decided to retain the existing go-live date until a new date could be determined. At that time a formal decision was made to change the go-live date. The utility’s objective was to change the go-live date only once.

Knowledge Transfer. One of the greatest fears of a utility has been that when the vendor leaves there will be no one left at the utility with knowledge of the system. Yet surprisingly, only a few utilities had formal knowledge transfer programs put in place as a specific activity in the work program.

Access to Historical Information. Strategy regarding how the utility will access information not converted into the new CIS was often poorly planned for. Questions like: “Will the existing billing system remain accessible, and for how long?” “Will there be another secondary system used?” “How does the purge/archive process work in the new CIS and how will the utility access that information?” were not addressed.

Late Code Drops – Poor Code Quality. Unfortunately, utilities have experienced late code drops from their vendor or code that when tested was found to be of poor quality. This impacted development activities which many times infringe on the start of testing activities.

Conversion Is Tough. Conversion was usually a lengthy and complicated process. Often there were multiple sources of data which had to be converted. In addition, in some cases the utility did not have people who are knowledgeable about the existing data, and on the other side, the vendor did not assign personnel with in-depth knowledge of the new CIS.

Insufficient Testing Time. It is a notorious fact that no matter how well a project is planned, if design and development activities take longer than expected, testing time is shortened to compensate. In these cases, testing was not as thorough and often multiple tests were executed at the same time, e.g. system testing, integration testing, performance testing, and user acceptance testing.

We know that 50% of utilities engaged in a CIS project are involved with an implementation effort. These utilities are constantly monitoring their projects and addressing project issues as they arise. While there are many challenges a utility may experience on a CIS project, one thing is certain, over time we find utilities are having greater success with their CIS installations than they have in previous years. All parties can and must work together toward a common goal of a successful CIS installation.

About the Author

Greg Galluzzi is a Senior Vice President of Five Point Partners with 28 years of experience with CIS solutions for the utility industry. He is the former CEO and founder, TMG Consulting which was aquired by Five Point in January 2009. He is a recognized CIS and utility industry expert and has participated in over 300 customer system initiatives offering comprehensive knowledge of planning, analysis, design, and installation.

 

 

 

©2009 Five Point Partners All Rights Reserved. Direct #512-288-2655 Contact the Webmaster

Home | Marketplace | News | RFP | Articles | Events | Site Map