There are many reasons why a CIS initiative fails, the following
areas of risk have been identified and presented for consideration.
CIS is not a proven solution.
The industry has moved from the implementation of custom developed
solutions, to the use of design guides or codeware customized
specifically for the utility, to product solutions with an 80
percent to 90 percent product fit. In today's market a primary
requirement is for the CIS product to be installed at a minimum
of one utility similar in size and services provided. Those utilities
selecting products still in development or immature products with
a minimal installed base have increased their risk exponentially
of extended implementation timeframes, cost overruns, functional
deficiencies, and in worst case scenarios outright project failures.
Poor contract, scope and responsibilities.
A major source of project confusion can be attributed to poor
contract language, unclear scope definition and undefined responsibilities.
Many times the installation effort is initiated without the identification
of the project components necessary for a successful implementation
effort. In other instances, components or constructs may have
been discussed but never adequately documented and agreed to.
During the implementation effort the phrase “I assumed you
were doing that.” is a strong indicator that insufficient
time was spent in defining project scope and specific responsibilities.
Unrealistic expectations, timeframes and poorly defined
costs.
Closely associated with second item, contracting parties frequently
enter the installation phase with unrealistic expectations of
the other party. This is why it is so important to perform an
adequate level of due diligence during the evaluation and selection
effort. In a number of efforts reviewed by TMG, project timeframes
and identified costs did not adequately allow for successful installation
of the defined solution. Many times project costs and associated
project risks are minimized in order to obtain approval for the
installation effort only to require subsequent funding requests.
Lack of available vendor resources.
Today's level of CIS market activity is significantly down compared
to recent years. As a result, layoffs, early retirement, etc.,
have left many vendor's struggling to adequately staff projects
with knowledgeable product resources. A number of vendors have
attempted to solve this problem by forming relationships with
Solution Integrators (SI) to supplement staff. However, the use
of SI's comes at a higher price tag resulting in the utility paying
high hourly rates for inexperienced product personnel. On the
other side, a few vendors continue to rely on internal consulting
groups to provide necessary project services. These groups are
spread very thin especially among fast growing CIS vendors with
sales quickly outpacing available resources.
Poor handoff from vendor sales to vendor operations.
Unfortunately, most selection efforts and final contract negotiations
are conducted with vendor sales personnel. Many times the details
of the agreed upon solution are never reviewed by vendor personnel
responsible for the installation effort. As a result, solutions
are negotiated which the vendor is not capable of fulfilling and
projects are planned and initiated which do not reflect the negotiated
solution and utility expectations. Vendors are beginning to add
operational personnel to their sales teams and require extensive
review and approval throughout the organization for new sales
contracts. However, the issue remains a significant problem.
Customize rather than configure system.
For a utility to successfully implement and fully realize the
ongoing benefits of a product solution it must minimize customization
work. Vendors continue to enhance product flexibility through
configuration capabilities. Unfortunately, many utilities require
the product to conform to utility specific business requirements
and processes. The utility should only consider initial customization
around required rates and tariffs. All other customization should
be delayed until the system has been used in production. Utilities
are modifying business processes, rules of service, meter configurations,
and even rate structures as necessary to utilize the software.
Every customization or interface included within project scope
increases the work effort and associated project risk.
Utility does not dedicate project resources.
The utility tends to place all blame on the vendor for project
troubles. In reality, both the vendor and the utility are the
source of problems. One of the biggest issues which the utility
faces is the inability to adequately staff project positions with
qualified business and technical staff. Historically, TMG has
seen part-time assignment with staff members still responsible
for production work or the utility assigns it's most inexperienced
or ineffective people to the project. More and more utilities
are waking up to the issue and backfilling for key personnel allowing
them to be dedicated to the project.
System is placed into production before its ready.
The biggest downfall of any project is the implementation of a
system which is not ready for production. At a workshop attended
by 30 utilities who recently implemented a CIS solution all 30
indicated they had implemented their system before it was ready
and did so to meet Executive/Board/Council expectations around
a go-live date which had been promised at the time the solution
was approved. While not as common there is another extreme where
a utility delays implementation until the system is 100 percent
complete—obviously this never occurs and the system is never
implemented.
Users and customers not prepared. The project
team and certainly the vendor is focused on the design, configuration,
testing and implementation of the new solution. Training and communication
becomes the responsibility of the utility and is usually under
funded, under estimated and under delivered. User acceptance testing
never occurs, user classroom training is limited without mock
production, refresher, or ongoing education activities, and customer
communication is limited to a single bill insert notifying them
of the new system. It is the curse of most projects that while
they are technical achievements they are business failures with
extensive resistance, business process issues, education issues,
and customer confusion.
Lack of executive involvement. The biggest underlying
reason most projects fail is the lack of strong executive involvement
and support of the project during its entire life-cycle. Most
efforts are initially approved by the executive team with their
involvement not occurring again until additional funding is requested,
timeframes are extended, or project success is placed in jeopardy.
Usually executive communication and support for the project occurs
at the highest levels in the utility and never effectively filters
down to the staff level. This lack of communication usually fuels
staff resistance or a perception of “This system will never
be placed into production so why worry about it.” syndrome
which undermines staff participation and buy-in to the solution.
Executive involvement is more than a once a month status report
it is daily interaction, visibility and commitment by key executives
to the success of the effort.
UtiliPoint's Emerging Technologies IssueAlert articles are
compiled based on the independent analysis of UtiliPoint consultants,
researchers, and analysts. The opinions expressed in UtiliPoint's
Emerging Technologies IssueAlert articles are not intended to
predict financial performance of companies discussed, or to be
the basis for investment decisions of any kind. UtiliPoint's sole
purpose in publishing its Emerging Technologies IssueAlert articles
is to Offer an independent perspective regarding the key events
occurring in the energy industry, based on its long-standing reputation
as an expert on energy issues.
©2004, UtiliPoint International, Inc. All rights reserved.
This article is protected by United States copyright and other
intellectual property laws and may not be reproduced, rewritten,
distributed, redisseminated, transmitted, displayed, published
or broadcast, directly or indirectly, in any medium without the
prior written permission of UtiliPoint, Inc.